bcee4405

7.3.4. Removal and installation of the generator

Details of assembly of the generator are shown on an illustration.

Assembly of the generator

1 — the Stator
2 — the Rotor with contact rings
3 — the Built-in fans

4 — the Rectifier
5 — tension Regulator

Disconnect a negative wire from the battery.

4-cylinder engines

 PERFORMANCE ORDER

  1. Remove a casing (3 on an illustration) over the inlet pipeline, Ý/m the valve (4) ventilations of a case and valves of constant pressure.
  1. Weaken a tension (5) of a belt of the drive of auxiliary units and remove it then turn out the top bolt of the generator (6).
  2. Mark and give a nut (7) of the right support of the engine.
  3. Give a nut of a back support of the engine.
  4. Remove a lobby of section of an exhaust pipe (see the Head of the Power supply system and production of the fulfilled gases) and a hose between the pallet of a case and an oil separator.
  1. Disconnect an electrical wiring from contacts of B and the D generator and turn out the lower bolt of the generator.
  1. Turn the generator down, between the steering mechanism and an intermediate shaft, then insert a strut between the transmission and a stretcher and remove the generator
  2. Installation is made as it should be, the return to an order of dismantle of components.

Petrol V6 engine

 PERFORMANCE ORDER

  1. Weaken a tension of a belt of the drive of auxiliary units and remove it a natyazhitel.
  2. Remove the right forward wheel.
  3. Remove the lower protection cover of a wheel arch.
  1. Turn out 6 bolts of a pulley (7 on an illustration), remove D/V of pressure of motive oil (8) and the right power shaft (9).

Zakuporte an opening under D/V of pressure of motive oil.

  1. Disconnect an electrical wiring and a sleeve of air cooling from the generator.
  2. Give 2 bolts of fastening of the generator and remove it through the right wheel arch.
  3. Installation is made as it should be, the return to an order of dismantle of components.

Diesel engine

 PERFORMANCE ORDER

  1. Weaken a tension of a belt of the drive of auxiliary units and take off a belt from pulleys.
  1. Disconnect an electrical wiring from the generator, turn out bolts of its fastening and remove the generator.
  1. Installation is made as it should be, the return to an order of dismantle of components.